Ghana Construction Pricing Guide: Labour, Materials, and Plant Hire (Q2 2026)

Quick Answer

Key Ghana construction rates for Q2 2026: cement GHS 101/bag (Ghacem Tema Depot, Greater Accra); rebar HT 12–20mm GHS 9,800/tonne ex-yard Accra (K OFORI, April 2026); backhoe hire GHS 4,600/day; NPA diesel GHS 16.10/litre; NTC minimum wage GHS 21.77/day. All figures are sourced from Ghanaian supplier surveys, NPA, and NTC published data. Rates are region-attributed and rate-dated.

This page is a structured reference to Exacto's Q2 2026 Ghana construction pricing data. All figures are sourced from Ghanaian supplier surveys, NPA published pump prices, and NTC published wage rates. Rates are region-attributed and rate-dated — the two pieces of information without which a construction cost figure is not independently verifiable.

Use this as a benchmarking reference. If your current estimate uses figures that diverge significantly from these, that divergence needs an explanation — either a different region, a different supplier, or a different rate date.

1. Labour Rates

The National Tripartite Committee (NTC) published a construction minimum wage of GHS 21.77/day effective January 2026 — a 9% increase from 2025. This is the statutory floor. In practice, skilled trades command multiples of this rate.

Trade / Task Greater Accra Rate National Benchmark Unit
NTC Minimum Wage (all trades) GHS 21.77 GHS 21.77 per day
Bricklaying / Blockwork GHS 213 GHS 200 per m²
Concreting (place and compact) GHS 213 GHS 200 per m²
Excavation (manual) GHS 120 GHS 100 per m³
Site Clearance GHS 120 GHS 100 per m²
Compacting GHS 18 GHS 16 per m²
Carpenter (formwork / shuttering) GHS 120–150 GHS 120 per day
Steel Bender / Fixer GHS 120–150 GHS 120 per day
Mason GHS 120–150 GHS 120 per day
General Labourer GHS 100–120 GHS 100 per day
Tree Cutting (600–1,500mm girth) GHS 200 GHS 180 per tree
Tree Cutting (1,500–3,000mm girth) GHS 220 GHS 200 per tree
Tree Cutting (over 3,000mm girth) GHS 250 GHS 230 per tree

Sources: NTC Minimum Wage Notice January 2026; Exacto supplier survey Q2 2026 (Greater Accra Masonry Crew, Accra Concrete Crew, Accra Earthworks Crew, National Supplier benchmarks).

2. Plant Hire Rates — Greater Accra (Q2 2026)

All plant hire rates below are dry hire — they exclude fuel, operator wages, and mobilisation costs. A complete plant cost line in your estimate must add all four components. Fuel is computed at NPA GHS 16.10/litre (see Section 3). Mobilisation costs vary by transport class (flatbed or lowbed) and distance from depot.

Equipment Daily Hire Rate Typical Output Fuel Consumption
Backhoe Loader — Normal Soil Excavation GHS 4,600/day 45 m³/day 55 L/day
Backhoe Loader — Backfilling and Spreading GHS 4,600/day 35 m³/day 55 L/day
Backhoe Loader — Hard Laterite Excavation GHS 4,600/day 30 m³/day 55 L/day
Backhoe Loader — Loading Aggregates GHS 4,600/day 90 m³/day 55 L/day
Excavator 20T — Trench Excavation GHS 17,500/day 110 m³/day 140 L/day
250HP-D8 Bulldozer — Reduced Level Excavation GHS 17,500/day 80 m³/day (or 5,000 m²/day clearing) 160 L/day
Mechanical Compactor + Operator GHS 7,000/day 8 m³/day 40 L/day
Compressor + Rock Drill (per drill) GHS 9,200/day 6 m³/day (rock breaking) 60 L/day

Source: Exacto earthworks plant database, Greater Accra rates, valid from April 2026 (+15% equipment escalation from 2025, +9% labour). Mobilisation transport costs are additional: flatbed GHS 1,050–1,575; lowbed GHS 3,000–5,250 depending on equipment class. Banksman rate GHS 165/day.

3. Diesel — The Hidden Multiplier in Every Plant Cost

The National Petroleum Authority (NPA) published a pump price of GHS 16.10/litre for diesel in April 2026. This is not a background detail — it is a primary cost driver for every plant-intensive trade.

What GHS 16.10/litre means in practice:

An estimate that uses the hire rate without adding fuel, operator, and mobilisation understates the all-in plant cost by 20–35% for most equipment. Exacto computes the full all-in cost from each component; the hire rate is the starting point, not the ending point.

4. Material Unit Prices — Indicative Accra Market Rates (Q2 2026)

Material Rate Unit Basis / Supplier
Cement (general, Ghacem Tema Depot) GHS 101 per 50kg bag Delivered inclusive, Greater Accra
Cement (national benchmark) GHS 100 per 50kg bag Delivered inclusive, national fallback
Cement CEM I 42.5R (K OFORI ex-yard) GHS 109 per 50kg bag Ex-yard, buyer collects, Greater Accra
Cement CEM II 32.5R (K OFORI / Cimaf) GHS 81 per 50kg bag Ex-yard, buyer collects, Greater Accra
Concrete Blocks (6") GHS 6.20 per unit National benchmark (2026), minimum 250 units/delivery
Rebar HT 12mm GHS 9,800 per tonne Ex-yard, K OFORI Steel Yards Accra (from April 2026); free delivery within 5km for ≥2t orders
Rebar HT 16mm GHS 9,800 per tonne Ex-yard, K OFORI Steel Yards Accra (from April 2026)
Rebar HT 20mm GHS 9,800 per tonne Ex-yard, K OFORI Steel Yards Accra (from April 2026)
Granite Aggregate — 3/4" (Shai Hills / Nana Yaw) GHS 200 per m³ delivered GHS 3,800/trip ÷ 19m³, Nana Yaw Shai Hills Quarry, Greater Accra
Granite Aggregate — 3/8" GHS 232 per m³ delivered GHS 4,400/trip ÷ 19m³, Nana Yaw Shai Hills Quarry
Quarry Dust GHS 253 per m³ delivered GHS 4,800/trip ÷ 19m³, Nana Yaw Shai Hills Quarry
Laterite (Nana Yaw / Amasaman) GHS 89–158 per m³ GHS 1,700/trip ÷ 19m³ (Nana Yaw); GHS 157.89/m³ ex-pit (Amasaman). Greater Accra.
Plywood Sheet 4ft × 8ft (local grade) GHS 335 per sheet In God We Trust Timber Yard, Greater Accra (ex-yard, free delivery within 15km)
Mortar (pre-mixed bag) GHS 45 per bag National benchmark 2026, delivered inclusive

Sources: Exacto materials database, valid_from 2026-01-01 to 2026-04-01+ rows. Supplier references: Ghacem Tema Depot, K OFORI Steel Yards Accra, Nana Yaw Shai Hills Quarry, Amasaman Laterite Pit, In God We Trust Timber Yard, National Supplier Logistics benchmarks. All prices are indicative market benchmarks and should be confirmed with suppliers at tender stage.

5. Regional Price Differentials

These Accra-region figures are the baseline. Expect the following adjustments for other regions:

Exacto stores region-specific rate rows for each material category. When you set your project region at setup, the platform applies the correct regional rates automatically — the right supplier, the right base rate, and the right haulage band for your site distance.

6. Haulage Cost Structure

Most construction materials in Ghana are priced ex-origin — the quoted rate is the ex-quarry or ex-yard price. Transport to site is a separate cost that must be built into the estimate explicitly.

Exacto applies distance-banded haulage multipliers:

Worked example: A project in East Legon is approximately 45km from Shai Hills quarry. For materials priced purely ex-origin — say laterite at GHS 89.47/m³ ex-pit — the 16–50km band applies a 2.0× multiplier to the transport component, making the all-in delivered cost materially higher than the ex-pit rate.

An estimate that records only the ex-origin rate and ignores haulage will understate cost on every bulk material line — aggregate, laterite, blocks, sand — by an amount that grows with project distance from the supply point.

These Are the Rates Exacto Uses

The figures on this page are drawn from Exacto's live Ghana pricing database — the same database your BOQ calculations run against when you use the platform. Region-aware, rate-dated, and built from Ghanaian supplier data. Not a conversion. Not an approximation.

Start Estimating Free